Tekirdağ B CCPP DCS Rehabilitation Project
Tekirdağ B CCPP DCS Rehabilitation Project
A contract was signed on September 13, 2024, with TEMSAN Inc. General Directorate for the rehabilitation and renewal of the Distributed Control System (DCS) of the Tekirdağ B Natural Gas Combined Cycle Power Plant, which has an installed capacity of 478 MWe.
The scope of the project includes the DCS systems of:
• Two (2) Heat Recovery Steam Generators (HRSGs),
• One (1) Steam Turbine,
• And the auxiliary systems of the plant.
As of today, the rehabilitation works are ongoing.
This page updated at 6 Ağustos 2025 07:36